Tirrawarra LLP Upgrade

Santos, (Cooper MSA 2023), SA
Upgrade of Tirrawarra facility by integrating the LLP compression facility into the existing satellite. Global installed piping from the LLP facility to the tie-ins adjacent the Tirrawarra slug catcher. Scope included civil works, extensive large diameter high pressure piping within active facility, including pigging facilities, as well as installation of the pipe supports, valve manifold skid and new concrete footings.