Moomba 50 MLR (UNO)

Santos, (Cooper MSA 2022), SA
Cut into the existing Moomba 50 gas flowline to install additional midline risers.

Scope included shut down of FL50, isolate, cold cut flowline. Install fabricated frame to support flowline and S bends. Concrete footings and steel supports, valves, golden weld pups onto existing flowline to avoid NDT. Above ground construction and commissioning prior to returning FL50 to service.