Nov 2022 – Sep 2023
APA Group, $5.6M, SA & NSW
Three facility upgrades including installation of pressure reduction stations (PRS) to increase gas transportation by 25%.
Moomba (SA): Installation of an additional meter run and flow control run DN300/DN400 piping. All mechanical and electrical scope.
Binerah Downs (NSW): Installation of an additional parallel pressure reduction control line around the existing class break skid. DN350 piping, 2 off hot tap tie-ins, live line excavations and civil works, All electrical, mechanical and fabrication scope. Remote worksite, Project delivered within schedule.
Bulla Park (NSW): Installation of two PRS skids, DN550 – DN300 piping installation, PRA/shutdown piping tie-ins, live line excavation, construction of facility pad. All mechanical scope, structural scope (concrete support footings), dry vacuum excavation. Electrical scope included earthing cable (MEG) runs / conduit runs. Design optimisation at 80%. Project completed ahead of schedule ~ 3 days. Several unidentified buried services. Very remote site.
East Coast Grid Expansion (ECGX)